Handover

14 min1 clickable picture1 handover lab6 pack sections5-min video review
In 30 seconds

Picture: handing over a car with the manual in the glove box, a spare key cut, and the new driver having already driven it while you sat in the back seat.

The problem Kavish hands over a claims triage system (a composite example) that went live cleanly: 4,200 claims a week routed, accuracy at 91 percent, the sponsor delighted. Three months later he gets a call at midnight. The one operator who understood the system has left the company. Her replacement can log in, but cannot restart a stuck queue, cannot tell a model fault from a data fault, and does not know which vault holds the service account password. In one week, 380 claims sat unrouted for more than a day, and 2 small incidents became a 3 day backlog because every fix waited on Kavish. The system had not failed. The handover had. Only one person could operate it, and that person was no longer in the building.
The plan for this chapter
  1. Why systems that work still fail at handover, and what the bus factor really costs.
  2. The handover pack: six sections, and what belongs in each one.
  3. Shadowing, reverse shadowing, and the road to running it alone.
  4. A lab: audit a handover pack and find the gaps before the customer does.
  5. Acceptance sign-off, the support rota, and the silent week that ends the job.

After this chapter you can:

Next: the words you will see.

Words you'll meet

Runbook
A step by step guide for one routine job or known failure, written so a competent stranger can follow it. Example: "Queue stuck above 500 messages: check the worker, restart it, verify the count falls."
Handover pack
Everything you transfer to the customer: documents, access, and records. Example: runbooks, architecture notes, the known issues list, and training records in one agreed place.
Shadowing
The operator watches you work a real task and asks questions, while you explain each decision out loud. Example: an operator watches you clear a stuck queue on a live shift.
Reverse shadowing
The operator does the work while you watch, silent unless they are about to cause harm. Example: the operator restarts the service alone while you note gaps.
Acceptance criteria
The written, testable conditions the customer checks before signing the work complete. Example: "The on call operator can restore service from backup in under 30 minutes, unaided."
Support rota
The schedule naming who is responsible for the system at each hour, and who is backup. Example: two operators alternate weekly, with a manager as second backup.
Escalation path
The agreed chain of people to contact, in order, when the person on duty cannot fix a problem. Example: operator, then team lead, then vendor support, then the sponsor.
Known issues list
The honest record of faults, quirks, and workarounds still in the system at handover. Example: "The nightly report fails if a file name contains a space; rename and rerun."
Training session
A planned session where operators practise real tasks from the runbooks, not a slide presentation. Example: each operator runs a restart, a rollback, and a restore.
Bus factor
How many people could be lost before nobody can run the system. Example: a bus factor of one means one resignation orphans a working system.

Next: why a working system still failed, three months after a clean go-live.

Step 1: Why handover fails, even when the build succeeds

Most handovers fail in the same quiet way. The builder knows the system in their hands: which log line matters, which restart is safe, which warning is noise. None of that feels like knowledge. It feels like common sense, right up until the builder leaves and the common sense leaves with them. In the composite example above, nothing is a technology fault: the queue still worked, the model still scored 91 percent. What was missing was everything around the technology:

A simple test exposes all of this before it costs anyone a weekend. Ask: if the builder and the lead operator both went on leave tomorrow, who restarts this system, who answers the first incident, and where do they read how? If any answer is a name rather than a document and a rota, the handover is not done, whatever the project plan says.

The rule of this chapter: you are not finished when the system works. You are finished when the system works without you, run by people who did not build it, on a bad day, from documents they trust. And handover starts at the beginning of the engagement, not the end: a handover compressed into the last three days produces a pack nobody has practised with, which is the midnight phone call waiting to happen.

Next: the pack itself, section by section.

Step 2: The handover pack

The handover pack is the single agreed place where everything the customer needs lives. Not your laptop, not a chat thread, not a folder only you can open. Six sections cover a working system. If one is empty, say so in writing and agree who fills it and by when: a known gap is a risk managed, a silent gap is a trap.

  1. Runbooks. One per routine job and one per known failure: starting and stopping, deploying, rolling back, restoring from backup, clearing queues. Each states the symptom, the check, the fix, and how to confirm it worked. Observability (Chapter 73) tells the operator what to look at; the runbook tells them what to do about it.
  2. Architecture notes. What the system is made of and how the parts connect: services, data stores, feeds, and the design diagram updated to match what shipped. The infrastructure definitions from Chapter 71 (Infrastructure as code and containers) belong here too: a customer who cannot rebuild the environment does not fully own the system.
  3. Credentials and access transfer. Every account, key, and certificate, where each sits in the customer's own vault, who owns it, and when it expires or rotates. Passwords move under the customer's control, never by email. Data governance (Chapter 68) sets the rules for who may hold what; handover proves the transfer followed them.
  4. Known issues list. Every fault, quirk, and workaround still live at handover, written plainly. Hiding one to smooth the sign-off destroys trust when it surfaces, and it always surfaces.
  5. Training records. Who was trained, on which tasks, on which dates, and who has passed reverse shadowing on each critical job. This is how you know the bus factor is above one for every task that matters.
  6. Support rota and escalation path. Who is on duty, who is backup, and the ordered chain to escalate through. Covered fully in Step 5.

Written as a checklist the customer can tick off at sign-off, the pack looks like this:

Handover pack checklist: claims triage system
Owner after handover: customer operations team
Location: customer wiki, section Operations / Claims Triage

[ ] Runbooks (each tested by an operator, not just written)
    [ ] Start, stop, restart; deploy and roll back
    [ ] Restore from backup; clear a stuck queue
    [ ] Model returning errors: checks and fixes
[ ] Architecture notes
    [ ] Diagram matches the live system (checked 2026-11-20)
    [ ] Data flows, feeds and owners listed
    [ ] Infrastructure definitions handed over (Chapter 71)
[ ] Credentials and access
    [ ] All service accounts in the customer vault
    [ ] Expiry and rotation dates listed
    [ ] Builder access removed or reduced to agreed level
[ ] Known issues list: 6 open, each with a workaround
[ ] Training records: 3 operators, all critical tasks covered twice
[ ] Support rota and escalation path published and tested

Two habits make a pack real instead of decorative. First, every runbook is tested by someone who did not write it, following only the words on the page. If they get stuck, the runbook is wrong, not the reader, and you fix the page on the spot. Second, the pack lives where the customer already works. A beautiful pack in a tool the customer abandons when your licence ends is a pack that does not exist.

Next: how operators actually learn the system, in three stages.

Step 3: Shadowing, reverse shadowing, and going solo

Documents transfer information. Only practice transfers skill. The route from watching to owning has three stages, and skipping the middle one is the most common handover mistake in the field. Press next to walk the route.

On a phone, swipe the picture sideways.

From shadowing to running it alone An operator first shadows the builder on real tasks, then reverse shadows by doing the work while the builder watches silently, then trains others, and finally runs the system for a silent week with the builder saying nothing before acceptance sign-off. Shadowingyou work,they watch Reverseshadowingthey work, you watch Trainingsessionspractice and teach Silent weekthey run it,you say nothing Sign-offcriteria met Gaps loggedfix and repeat
  1. The operator watches you run real work: a deploy, a restart, a live incident. You narrate every decision, including the checks that turned out fine, because the judgement is the lesson.
  2. Now the operator drives and you watch, hands off the keyboard. You speak only to prevent harm. Every hesitation marks where the runbook or the training needs work.
  3. The operator practises each critical task from the runbook alone, then teaches it to a second operator. Teaching is the deepest test of understanding, and it raises the bus factor.
  4. For one full week the customer team runs everything: shifts, incidents, routine jobs. You are reachable for genuine emergencies only, and you log every time they needed you.
  5. If the week passed inside the agreed acceptance criteria, the customer signs. The signature records a fact everyone has watched happen.
  6. Any gap the week exposed gets fixed in the pack or the training, and the affected task is practised again. A failed week is information, not a disaster, as long as it happens before you leave.
WatchingDoingGapsOwned

Where the picture breaks down: the stages look tidy, but real incidents do not schedule themselves inside your training plan. That is the point of practising deliberately: the restart, the rollback, and the restore can all be rehearsed on a quiet Tuesday, so the first time an operator does them under pressure is not the first time they do them at all. A good training session is mostly hands on keyboards, in groups of three or four, and ends by updating the runbook with whatever the group found unclear. Nobody ever learned to restore a backup from a slide.

Next: the lab, where you audit a pack that looks finished and is not.

Step 4: Lab: audit a handover pack

Why: packs fail on missing pieces, not on bad writing. Auditing one against the six sections teaches you to spot the gaps that turn into midnight calls.

Here is the handover record for a document search system (a composite example), one week before the builder leaves. The sponsor believes it is ready for sign-off. Audit it against the six pack sections from Step 2 and the test from Step 1: could two named operators run this alone on a bad day?

ItemWhat the record shows
Runbooks4 written: start and stop, deploy, clear queue, model errors. None followed by anyone except the author. No rollback runbook, no restore runbook.
Architecture notesDiagram from the design phase, 4 months old. Two services added since are missing. Data feeds listed with owners.
Credentials and accessService accounts listed. Passwords still in the builder's vault, transfer booked for the final day. One API key expires in 19 days, no rotation owner named.
Known issuesList exists with 5 issues and workarounds. A sixth, a report that fails on file names with spaces, was mentioned in a meeting but never added.
TrainingOne operator, Priya, shadowed for 3 sessions. Reverse shadowing not started. No second operator trained, no records kept.
Support rotaDrafted: Priya on duty every week, no backup named. Escalation path lists the builder's mobile as step one.

Lab: One week before the builder leaves, the sponsor believes this handover pack for a document search system is ready for sign-off. This lab runs in your browser and needs JavaScript enabled.

In the field An FDE (composite) ran the silent week on a forecasting system with 2 operators and 11 runbooks. The week produced 4 incidents. The operators fixed 3 alone from the runbooks. The fourth, a certificate expiry nobody had listed, became a new runbook, a calendar reminder, and a line on the known issues list before sign-off. In the 90 days after the builder left, the customer raised 2 support questions, both about new features, and none about running the system. That is what a finished handover looks like in numbers.

Next: sign-off, cover after you leave, and the final test.

Step 5: Sign-off, the rota, and the rebuild test

Acceptance criteria turn "we think it is ready" into checks both sides can run. Write them early, with the customer, and make each one testable rather than arguable in a meeting. Strong criteria sound like this: each critical task completed unaided by at least two named operators; a restore from backup demonstrated inside the agreed time; every credential in the customer vault with a named rotation owner; the rota covering the next 4 weeks with a backup on every shift. Weak criteria sound like "documentation provided". Provided is not the same as usable, and the silent week shows which one you have.

The support rota names who is on duty, who backs them up, and how a shift handover happens. Expect it to be used more right after you leave, not less, and agree a short tail of support, for example two clinics a week for the first month, so questions collect in one place. Change management (Chapter 76) covers how the system keeps evolving; the rota is who holds it steady while it does. The escalation path is the rota's partner: an ordered list with names, roles, and contact routes the customer controls, from the operator on duty to their team lead, the service owner, any vendor contract, and finally the sponsor. Test it once with a drill message before you leave; a path never dialled is a hope, not a path. And note what is not on it: you. A path that starts with the departed builder is the midnight call from Step 1, scheduled.

Then comes the final proof: the rebuild test. In its full form, the customer team takes the pack and the infrastructure definitions, rebuilds the system in a clean environment, then runs it for a week with you silent. The softer form is the silent week from Step 3 plus a supervised restore and redeploy. Either way the team demonstrates, on systems they control, from documents they own, that your absence changes nothing. Log every intervention you had to make: each is a gap to close, and the count should reach zero, or near it with agreed owners, before anyone signs. Sign-off is then a short, shared moment: walk the criteria, show the evidence (training records, the silent week log, the tested rota), record accepted gaps on the known issues list with owners and dates, and have the customer sign as the new owner of the system, because that is what they now are.

Next: a prediction, two quick checks, then the final quiz.

Information is not skill. Until operators have done the work while you watch, and then without you, the handover is a plan, not a result.

Quick checks

Mix-ups to avoid

Recap

Next: Chapter 78, "Closing the loop to product": turning everything the deployment taught you into changes the product team actually ships.